Converse agora com nosso suporte
Chat com o suporte

Identity Manager On Demand - Starling Edition Hosted - Risk Assessment Administration Guide

Starting risk index calculations

The risk index calculation is started by the following events:

  • A function was changed.

  • Objects in the source table have changed.

  • A scheduled calculation task is being run.

Risk index function was modified

The moment a function changes, a calculation procedure for the effected table column (target) is set up. There is exactly one procedure set up for each table column (target), which bundles all enabled functions for the table column. Then the risk indexes are calculated.

Data change in a source table

Once data in the source tables changes, the risk indexes are recalculated. To do this, a calculation task is queued in the DBQueue Processor. If the Calculate immediately option is set for a function, the risk indexes effected are calculated immediately. In this case, the calculation is not DBQueue Processor controlled.

The following changes to the source tables trigger recalculation

  • Objects are added or deleted

  • The origin of an assignment has changed.

  • The effectiveness of an assignment has changed.

  • Risk indexes were changed

  • Risk indexes were calculated

All other changes do not cause automatic recalculation of risk indexes. You can use a process plan task to calculate risk indexes so that changes made to them can take effect. This is required, for example, in order to take into account approval of attestation cases in calculated risk indexes. Functions that are not assigned to a source table are also only taken into account when scheduled recalculation is run.

Scheduled calculation task is run for the DBQueue Processor

To ensure that calculated risk indexes are continually update, taking all functions into account, you can configure a scheduled calculation task to calculate risk indexes. The Calculate risk index schedule is provided to do this. This schedule is disabled, by default. Enable it to recalculate the risk indexes on a scheduled basis. Adjust the activation times to suit your company’s requirements.

To enable the schedule for calculating risk indexes

  1. In the Designer, select the Base data > General > Schedules category.

  2. Select the Calculate risk indexes schedule in the List Editor.

  3. Click Enabled in the edit view.

  4. Save the changes.
Related topics

Weighting and normalization

You can calculate the risk index for an object type using different methods.

  1. Highest risk index of all assigned company resources

  2. Average of all assigned company resource risk indexes

  3. Highest weighted risk index of all assigned company resources

  4. Sum of all normalized to 1 and weighted assigned company resource risk indexes

In the default functions, the risk indexes are calculated by the first method.

NOTE: If calculation types for both weighting and normalization are implemented in risk index functions for one and the same target column, the risk index calculation does not determine a reasonable value.

The following applies to all of a target column's risk index functions: Only combine risk index functions with the Maximum (weighted) and Average (weighted) calculation types or functions with the Maximum (normalized) and Average (normalized) calculation types!

Weighting

In the calculation using method 3, the maximum and average values are determined of the risk index of all assigned company resources of an object type. This value is weighted with the given weighting. The highest weighted risk index is the calculated risk index.

Calculations using methods 1 and 2 occur when the weighting is given with the value 1 in all the relevant functions.

To calculate risk indexes using methods 1, 2, or 3

  • Select the Maximum (weighted) or Average (weighted) calculation type.

Normalization

In the calculations using method 4, the maximum and average values of the risk index for all assigned company resources of an object type are determined. This value is weighted. The sum of all weighted risk indexes of this object type is the calculated risk index.

The sum of the weightings must be exactly 1 within a calculation, because the range from 0 to 1 must be adhered to for the resulting risk index. That is why the weightings of all enabled functions for the same target column are normalized to 1. The risk index found is weighted with this normalized value. The normalized weighting is calculated from the weighting divided by the sum of all relevant weighted values. This results in the following formula for calculating the risk index:

To calculate risk indexes using method 4

  • Select the Maximum (normalized) or Average (normalized) calculation type.

The weighting is only relevant if there is more than one function for a target column because the result of normalization is exactly 1. In this case, calculations using method 4 return the same result as calculating with method 1. The difference between weighting and normalization is only relevant if more than one function is enabled for a target column. This is made clear in the following example.

Example:

Calculate the risk index for SAP user accounts from risk indexes of assigned SAP groups and structural profiles, and from SAP function risk indexes that match with the user accounts. Three SAP groups (G1, G2, G3) and two structural profiles (P1, P2) are assigned to a user account. The user account matches one SAP function (FS) exactly.

Risk Indexes

  • G1 = 0.2

  • G1 = 0.3

  • G1 = 0.4

  • P1 = 0.6

  • P2 = 0.7

  • SF = 0.5

Calculation type

  • By method 1: Maximum (weighted), weighting = 1

  • By method 3: Maximum (weighted)

    SAP group weighting factor: 0.6

    Structural profile weighting factor: 0.8

    SAP function weighting factor: 0.7

  • By method 4: Maximum (normalized)

    SAP group weighting factor: 0.6

    Structural profile weighting factor: 0.8

    SAP function weighting factor: 0.7

Table 7: Risk index calculation results
Calculation Method 1 Method 3 Method 4

Highest risk index of all assigned SAP groups

0.4

0.4

0.4

Weighting/Normalization

1 * 0.4 = 0.4

0.6 * 0.4 = 0.24

(0.6 / (0.6 + 0.8 + 0.7)) * 0.4 = 0.11428

Highest risk index of all assigned structural profiles

0.7

0.7

0.7

Weighting/Normalization

1 * 0.7 = 0.7

0.8 * 0.7 = 0.56

(0.8 / (0.6 + 0.8 + 0.7)) * 0.7 = 0.26667

Highest risk index of all matching SAP functions

0.5

0.5

0.5

Weighting/Normalization

1 * 0.5 = 0.5

0.7 * 0.5 = 0.35

(0.7 / (0.6 + 0.8 + 0.7)) * 0.5 = 0.16667

Highest weighted value/sum normalized value (= resulting user account risk index)

0.7

0.56

0.54762

Mitigating controls

Effective permissions of identities, roles, or user accounts are checked in the context of Identity Audit on the basis of regulatory requirements. Violation of regulatory requirements can harbor different risks for companies. To evaluate these risks, you can apply risk indexes to compliance rules, SAP functions, attestation policies and company policies. These risk indexes provide information about the risk involved for the company if this particular rule, SAP function or policy is violated. Once the risks have been identified and evaluated, mitigating controls can be implemented.

Mitigating controls are independent on One Identity Manager’s functionality. They are not monitored through One Identity Manager.

An example of a mitigating control is the assignment of system entitlements only through authorized requests in the IT Shop. If system entitlements are issued to identities through the IT Shop, a rule check can be integrated into the request’s approval process. System entitlements that would lead to a rule violation are therefore assigned not at all or only after gaining exception approval. The risk that rules are violated is thus reduced.

Defining mitigating controls

Mitigating controls can be defined in One Identity Manager functions.

Table 8: Object types with mitigating controls
Function Object type Application Available in Module
Compliance Compliance rules Reduces the risk connection with violating rules. Compliance Rules Module
Rule violations Reduces the risk connected with the exception approval of a concrete rule violation.
SAP functions Reduces the risk of SAP user accounts matching SAP functions. SAP R/3 Compliance Add-on Module
Attestation Attestation policies Reduces the risk connected with denied attestation cases. Attestation Module
Attestation Cases Reduces the risk connected with the denial of a concrete attestation case.
Company policies Company policies Reduces the risk connection with violating policies. Company Policies Module
Policy violations Reduces the risk connected with the exception approval of a concrete policy violation.

To edit mitigating controls

  • In the Designer, set the QER | CalculateRiskIndex configuration parameter and compile the database.

If you disable the configuration parameter at a later date, model components and scripts that are no longer required, are disabled. SQL procedures and triggers are still carried out. For more information about the behavior of preprocessor relevant configuration parameters and conditional compiling, see the One Identity Manager Configuration Guide.

Use SAP to assign mitigating controls to compliance rules, Manager functions or company policies.

You can assign mitigating controls directly to a specific rule violation when editing exception approval for rule violations in the Web Portal. You can assign mitigating controls direct to a specific attestation case during attestation in the Web Portal. You can assign mitigating controls directly to a specific rule violation when editing exception approval for policy violations in the Web Portal. For more information, see the One Identity Manager Web Designer Web Portal User Guide.

Detailed information about this topic
Documentos relacionados

The document was helpful.

Selecione a classificação

I easily found the information I needed.

Selecione a classificação