立即与支持人员聊天
与支持团队交流

Identity Manager 9.2.1 - Operational Guide

About this guide Simulating data changes in the Manager Scheduling operations activation times Re-applying templates Exporting data with the Manager Analyzing data and data changes Analyzing process monitoring in the Manager Schedules in One Identity Manager Mail templates in One Identity Manager Password policies in One Identity Manager Working with change labels Checking data consistency Compiling a One Identity Manager database Transporting custom changes Importing data with the Data Import Importing and exporting individual files for the software update Creating a One Identity Manager database for test or development from a database backup Initializing DBQueue Processor the after extending the server hardware Command line programs

Assigning change labels when saving in the Designer

To assign changes to a change label in the Designer

  1. In the Designer, select the Database > Commit to database menu item.

  2. In the toolbar, select the required change label in the Change label list. When the changes are transferred to the One Identity Manager database, the change label is applied to the changes affected.

  3. To assign individual changes to different change labels, use the Special change label context menu entry in the change log.

  4. Save the changes.

Related topics

Displaying content of change labels

To display the contents of a change label

  1. In the Manager or the Designer, select the Database > Change management menu item.

  2. In the Change management dialog, select the relevant change label in the Change label menu.

    If you used this change label to take snapshots of objects, the objects assigned to the change label are shown in the Tagged changes pane. The following functions are available:

    • To search within a change label, use Ctrl +F.

    • To restrict the information displayed to a single change label, click the arrow in the table header of a column and enter a filter text.

    • Use the context menu to change the order of the changes within a change label. This order is taken into account when the changes are transported.

    • The content of a change for an object is defined in XML format. It specifies whether a property is created, changed, or deleted with a change. To display an XML definition of a change, select Edit change data.

    If change labels reference objects, in the Assigned objects pane, you can see all the objects that are assigned to the change label.

TIP: In the Designer, you will find an overview of change labels in the Base data > General > Change label category.

Related topics

Locking change labels

If a change label is locked, no further changes can be booked to this label. For example, change labels can be locked and closed after they have been transported with the Database Transporter.

To lock a change label

  1. In the Manager or the Designer, select the Database > Change management menu item.

  2. In the Change management dialog next to the Change labels menu, click .

  3. Select a change label from the list and open the edit view using .

  4. Select the value True for the Locked property.

  5. Click the button.

  6. Click OK.

Related topics

Deleting change labels

You can delete a change label if you do not need it anymore.

To delete a change label

  1. In the Manager or the Designer, select the Database > Change management menu item.

  2. In the Change management dialog next to the Change labels menu, click .

  3. In the Change label dialog, select the change label and click the button .

  4. Confirm the security prompt with Yes.

  5. To close the Change label dialog, click Cancel.

  6. To close the Change management dialog, click OK.

Related topics
相关文档

The document was helpful.

选择评级

I easily found the information I needed.

选择评级