サポートと今すぐチャット
サポートとのチャット

Identity Manager 9.2 - CSV Connector User Guide

Removing a CSV file from the system connection

To remove a CSV file from the system connection

  1. Select the Configuration > Target system category.

  2. Click Edit connection.

    This starts the system connection wizard.

  3. On the Load CSV system file page, in the CSV system information view, specify the CSV files with which to set up the system connection. To remove a CSV file from the system connection, select the file and click . Click Next.

  4. Click Finish to end the system connection wizard.
  5. Select the General view and click Update schema.

  6. Confirm the security prompt with Yes.
  7. This reloads the schema data.

  8. Save the changes.
Related topics

Changing path to CSV system file

To change the CSV system file directory path

  1. Select the Configuration > Target system category.

  2. Click Edit connection.

    This starts the system connection wizard.

  3. On the Load CSV system file page, in the CSV system file view, select the correct CSV system file and click Next.

  4. Click Finish to end the system connection wizard.

Updating schemas

All the schema data (schema types and schema properties) of the target system schema and the One Identity Manager schema are available when you are editing a synchronization project. Only a part of this data is really needed for configuring synchronization. If a synchronization project is finished, the schema is compressed to remove unnecessary data from the synchronization project. This can speed up the loading of the synchronization project. Deleted schema data can be added to the synchronization configuration again at a later point.

If the target system schema or the One Identity Manager schema has changed, these changes must also be added to the synchronization configuration. Then the changes can be added to the schema property mapping.

To include schema data that have been deleted through compression and schema modifications in the synchronization project, update each schema in the synchronization project. This may be necessary if:

  • A schema was changed by:

    • Changes to a target system schema

    • Customizations to the One Identity Manager schema

    • A One Identity Manager update migration

  • A schema in the synchronization project was shrunk by:

    • Enabling the synchronization project

    • Saving the synchronization project for the first time

    • Compressing a schema

To update a system connection schema

  1. In the Synchronization Editor, open the synchronization project.

  2. Select the Configuration > Target system category.

    - OR -

    Select the Configuration > One Identity Manager connection category.

  3. Select the General view and click Update schema.

  4. Confirm the security prompt with Yes.

    This reloads the schema data.

To edit a mapping

  1. In the Synchronization Editor, open the synchronization project.

  2. Select the Mappings category.

  3. Select a mapping in the navigation view.

    Opens the Mapping Editor. For more information about mappings, see the One Identity Manager Target System Synchronization Reference Guide.

NOTE: The synchronization is deactivated if the schema of an activated synchronization project is updated. Reactivate the synchronization project to synchronize.

Starting synchronization

Synchronization is started using scheduled process plans. A scheduled process plan is added once a start up configuration is assigned to a schedule. Use schedules to define running times for synchronization.

NOTE: Synchronization can only be started if the synchronization project is enabled.

To run synchronization regularly, configure, and activate the a schedule. You can also start synchronization manually if there is no active schedule.

IMPORTANT: As long as a synchronization process is running, you must not start another synchronization process for the same target system. This especially applies, if the same synchronization objects would be processed.

  • If another synchronization process is started with the same start up configuration, the process is stopped and is assigned Frozen status. An error message is written to the One Identity Manager Service log file.

    • Ensure that start up configurations that are used in start up sequences are not started individually at the same time. Assign start up sequences and start up configurations different schedules.

  • Starting another synchronization process with different start up configuration that addresses same target system may lead to synchronization errors or loss of data. Specify One Identity Manager behavior in this case, in the start up configuration.

    • Use the schedule to ensure that the start up configurations are run in sequence.

    • Group start up configurations with the same start up behavior.

If you want to specify the order in which target systems are synchronized, use the start up sequence to run synchronization. In a start up sequence, you can combine start up configurations from different synchronization projects and specify the order in which they are run. For more information about start up sequences, see the One Identity Manager Target System Synchronization Reference Guide.

関連ドキュメント

The document was helpful.

評価を選択

I easily found the information I needed.

評価を選択