Managing Unix-Based Systems Setting Up Synchronization with a Unix-Based Target System Base Data for Unix-Based Target Systems Unix Host Unix user accounts Unix groups Reports about Unix Objects Appendix: Configuration Parameters for Managing Unix Appendix: Default Project Template for Unix-Based Target Systems

Setting Up an Initial Synchronization Project

NOTE: The following sequence describes how you configure a synchronization project if the Synchronization Editor is both:
  • In default mode
  • Started from the launchpad

Additional settings can be made if the project wizard is run in expert mode or is started directly from the Synchronization Editor. Follow the project wizard instructions through these steps.

To set up an initial synchronization project for a Unix-based target system

  1. Start the Launchpad and log on to the One Identity Manager database.

    NOTE: If synchronization is executed by an application server, connect the database through the application server.
  2. Select the entry Unix target system type. Click Run.

    This starts the Synchronization Editor's project wizard.

  1. Specify how the One Identity Manager can access the target system on the System access page.
    • If you have access from the workstation from which you started the Synchronization Editor, do not set anything.
    • If you do not have access from the workstation from which you started the Synchronization Editor, you can set up a remote connection.

      In this case, set the option Connect using remote connection server and select, under Job server, the server you want to use for the connection.

  1. Enter the connection data for the Unix host on the General connection settings page.
    1. Enter the server name or host's IP address in Server or IP.
    2. Enter the communications port for establishing the SSH connection in Port. The default communications port is the TCP port 22.
    3. Enter the user account and password for SSH login on the host.
    4. Click Test to test the connection. The system tries to connect to the host.
  2. Click Test in the Verify connection pane to test the connection to the host.
  3. Select the method to use for obtaining administrative permissions on the page Change to administrative context.
    • Select the method "Default" if the user already possesses administrative permissions.

    • Select the method "Sudo" if the current user logged in on the host can run administrative tasks as an administrative user. Enter the alternative user, for example "root", in User.

    • Select the method "su", if administrative tasks should be executed using a different user. Enter the login data of the other user in User and Password. The default user is "root".

  1. Verify the One Identity Manager database connection data on the One Identity Manager connection page. The data is loaded from the connected database. Reenter the password.

    NOTE: Reenter all the connection data if you are not working with an encrypted One Identity Manager database and no synchronization project has been saved yet in the database. This page is not shown if a synchronization project already exists.
  2. The wizard loads the target system schema. This may take a few minutes depending on the type of target system access and the size of the target system.
  1. Specify how system access should work on the page Restrict target system access. You have the following options:
    Table 7: Specifying Target System Access
    Option Meaning

    Read-only access to target system.

    Specifies whether a synchronization workflow should be set up to initially load the target system into the One Identity Manager database.

    The synchronization workflow has the following characteristics:

    • Synchronization is in the direction of "One Identity Manager".
    • Processing methods in the synchronization steps are only defined in synchronization direction "One Identity Manager".

    Changes are also made to the target system.

    Specifies whether a provisioning workflow should be set up in addition to the synchronization workflow to initially load the target system.

    The provisioning workflow displays the following characteristics:

    • Synchronization in the direction of the "target system"
    • Processing methods are only defined in the synchronization steps in synchronization direction "target system".
    • Synchronization steps are only created for such schema classes whose schema types have write access.
  2. Select the synchronization server to execute synchronization on the Synchronization server page.

    If the synchronization server is not declare as a job server in the One Identity Manager database yet, you can add a new job server.

    • Click to add a new job server.
    • Enter a name for the job server and the full server name conforming to DNS syntax.
    • Click OK.

      The synchronization server is declared as job server for the target system in the One Identity Manager database.

      NOTE: Ensure that this server is set up as the synchronization server after saving the synchronization project.
  1. Click Finish to complete the project wizard.

    This creates and allocates a default schedule for regular synchronization. Enable the schedule for regular synchronization.

    The synchronization project is created, saved and enabled immediately.

    NOTE: If the synchronization project is not going to be executed immediately, disable the option Activate and save the new synchronization project automatically.

    In this case, save the synchronization project manually before closing the Synchronization Editor.

    NOTE: The target system connection data is saved in a variable set, which you can change in the Synchronization Editor under Configuration | Variables if necessary.

To configure the content of the synchronization log

  1. To configure the synchronization log for target system connection, select the category Configuration | Target system.
  2. To configure the synchronization log for the database connection, select the category Configuration | One Identity Manager connection.
  3. Select General view and click Configure....
  4. Select the Synchronization log view and set Create synchronization log.
  5. Enable the data to be logged.

    NOTE: Certain content create a lot of log data.

    The synchronization log should only contain the data necessary for error analysis and other evaluations.

  6. Click OK.

To synchronize on a regular basis

  1. Select the category Configuration | Start up configurations.
  2. Select a start up configuration in the document view and click Edit schedule....
  3. Edit the schedule properties.
  4. To enable the schedule, click Activate.
  5. Click OK.

To start initial synchronization manually

  1. Select the category Configuration | Start up configurations.
  2. Select a start up configuration in the document view and click Execute.
  3. Confirm the security prompt with Yes.

NOTE: Following synchronization, employees are automatically created for user accounts in the default installation. If there are no account definitions for the host at the time of synchronization, user accounts are linked to employees. However, account definitions are not assigned. The user accounts are, therefore, in a "Linked" state.

To select user accounts through account definitions

  1. Create an account definition.
  2. Assign an account definition to the host.
  3. Assign the account definition and manage level to the user accounts in a "linked" state.
    1. Select the category Unix | User accounts | Linked but not configured | <host>.
    2. Select the task Assign account definition to linked accounts.
Related Topics

Show Synchronization Results

Show Synchronization Results

Synchronization results are summarized in the synchronization log. You can specify the extent of the synchronization log for each system connection individually. One Identity Manager provides several reports in which the synchronization results are organized under different criteria.

To display a synchronization log

  1. Open the synchronization project in the Synchronization Editor.
  2. Select the category Logs.
  3. Click in the navigation view toolbar.

    Logs for all completed synchronization runs are displayed in the navigation view.

  4. Select a log by double-clicking on it.

    An analysis of the synchronization is shown as a report. You can save the report.

To display a provisioning log.

  1. Open the synchronization project in the Synchronization Editor.
  2. Select the category Logs.
  3. Click in the navigation view toolbar.

    Logs for all completed provisioning processes are displayed in the navigation view.

  4. Select a log by double-clicking on it.

    An analysis of the provisioning is show as a report. You can save the report.

The log is marked in color in the navigation view. This mark shows you the execution status of the synchronization/provisioning.

Configuring the Log's Retention Time

Synchronization logs are stored for a fixed length of time. The retention period is set in the configuration parameter "DPR\Journal\LifeTime" and its sub parameters.

To modify the retention period for synchronization logs

  • Set the configuration parameter "Common\Journal\LifeTime" in the Designer and enter the maximum retention time for entries in the database journal. Use the configuration sub parameters to specify the retention period for each warning level.
  • If there is a large amount of data, you can specify the number of objects to delete per DBQueue Processor operation and run in order to improve performance. Use the configuration parameters "Common\Journal\Delete\BulkCount" and "Common\Journal\Delete\TotalCount" to do this.
  • Configure and set the schedule "Delete journal" in the Designer.

Customizing Synchronization Configuration

Customizing Synchronization Configuration

You have used the Synchronization Editor to set up a synchronization project for initial synchronization of an Unix host. You can use this synchronization project to load Unix objects into the One Identity Manager database. If you manage user accounts and their authorizations with One Identity Manager, changes are provisioned in the Unix-based target system.

You must customize the synchronization configuration in order to compare the database with the Unix-based target system regularly and to synchronize changes.

  • Create a workflow with the direction of synchronization "target system" to use One Identity Manager as the master system for synchronization.
  • You can use variables to create generally applicable synchronization configurations which contain the necessary information about the synchronization objects when synchronization starts. Variables can be implemented in base objects, schema classes or processing methods, for example.
  • Use variables to set up a synchronization project which can be used for several different hosts. Store a connection parameter as a variable for logging onto the hosts.
  • To specify which Unix objects and database object are included in synchronization, edit the scope of the target system connection and the One Identity Manager database connection. To prevent data inconsistencies, define the same scope in both systems. If no scope is defined, all objects will be synchronized.
  • Update the schema in the synchronization project, if the One Identity Manager schema or target system schema has changed. Then you can add the changes to the mapping.

IMPORTANT: As long as synchronization is running, you must not start another synchronization for the same target system. This applies especially, if the same synchronization objects would be processed.

  • The moment another synchronization is started with the same start up configuration, the running synchronization process is stopped and given the status, "Frozen". An error message is written to the One Identity Manager Service log file.
  • If another synchronization is started with another start up configuration, that addresses same target system, it may lead to synchronization error or loss of data. Plan your start times carefully. If possible, specify your start times so that synchronization does not overlap.

For more detailed information about configuring synchronization, see the One Identity Manager Target System Synchronization Reference Guide.

Detailed information about this topic
Related Documents