About this guide Simulating data changes in the Manager Scheduling operations activation times Re-applying templates in the Manager Exporting data with the Manager Analyzing data and data changes Analyzing process monitoring in the Manager Schedules in One Identity Manager Mail templates in One Identity Manager Password policies in One Identity Manager Working with change labels Checking data consistency Compiling a One Identity Manager database Transporting custom changes Importing data with the Data Import Importing and exporting individual files for the software update Creating a One Identity Manager database for test or development from a database backup Initializing DBQueue Processor the after extending the server hardware Command line programs Configuration of settings for the One Identity Manager tools

Enabling and disabling schedules

You can enable and disable schedules. Only enabled schedules can be run.

To enable a single schedule in the Designer

  1. In the Designer, select the Base data > General > Schedules category.

  2. Select the schedule.

  3. Set Enabled.

  4. Select the Database > Save to database and click Save.

To disable a single schedule in the Designer

  1. In the Designer, select the Base data > General > Schedules category.

  2. Select the schedule.

  3. Disable the Enable option.

  4. Select the Database > Save to database and click Save.

Related topics

Zeitpläne automatisiert ausführen

Aktivierte Zeitpläne werden automatisiert ausgeführt, wenn der Konfigurationsparameter QBM | Schedules aktiviert ist. In the Designer, check if the configuration parameter is set. If not, set the configuration parameter.

Um die automatisierte Ausführung aller Zeitpläne temporär anzuhalten, deaktivieren Sie im Designer den Konfigurationsparameter QBM | Schedules. This stops the schedules from being run automatically. However, you can still start schedules manually.

Related topics

Starting schedules immediately

Normally, schedules are started automatically. If necessary, you can start a schedule manually at any time.

NOTE: Before you start a schedule manually, check whether other processes that also need to be preprocessed by One Identity Manager will be run as a result.

To start a schedule in the Designer immediately

  1. In the Designer, select the Base data > General > Schedules category.

  2. Select the schedule.

  3. Click Start.

  4. Confirm the security prompt with Yes.

NOTE: The last processing time is not updated when the schedule is started manually.

Related topics

Creating and editing schedules

If necessary, you can change the default schedules or create new schedules.

To create a schedule in the Designer

  1. In the Designer, select the Base data > General > Schedules category.

  2. Select the Object > New menu item to create a new schedules.

  3. Edit the schedule’s main data.

  4. Select the Database > Save to database and click Save.

To edit a schedule in the Designer

  1. In the Designer, select the Base data > General > Schedules category.

  2. Select a schedule.

  3. Edit the schedule’s main data.

  4. Select the Database > Save to database and click Save.

Related topics
Related Documents

The document was helpful.

Select Rating

I easily found the information I needed.

Select Rating